Time Counting For Discharging Coal Cargoes By Geared Vessels At Indian Ports

When The Geared Vessels Should Be Considered Ready To Discharge?
One
feature of the contracts for the procurement of coal by the Indian
steel and energy companies on CFR terms basis is the buyers` requirement
to nominate geared bulk carriers suitable for discharge of coal cargoes
by grabs because the Indian ports do not have high-capacity cranes for
the discharge of coal.
The question of geared vessels` readiness to
discharge the coal cargoes was raised by Steel Authority of India Ltd.
in two charter party disputes to avoid the payment of demurrage charge
for the time lost by three geared vessels waiting for berth.
In 2014 Indian law case Steel Authority of India Ltd. v. Dampskibaselsbaket Norden A/S,
Steel Authority of India Ltd. rejected two demurrage claims under a
contract of affreightment for the carriage of cargoes of coking coal in
bulk from Newport News to Indian ports Vishakhapatnam and Haldia.
The
first cargo was shipped on board the vessel "Nord Fighter". The cargo
quantity on board the vessel was 51,544.726 MT of which a quantity of
25,189 MT had to be discharged at Vishakhapatnam and the balance of
26,355.73 MT had to be discharged at Haldia.
When the vessel arrived
at the port of Vishakhapatnam on 12th May 2008, the discharging berth
was occupied. The Master tendered NOR at 09:45 hours on the same day
from the waiting place.
The vessel berthed on 17th May 2008 at 17:00 hours and commenced discharging operations at 18:30 hours.
The
vessel arrived with a non-functional crane (crane no.3) which was under
repair and made available only on 20th May at 22:00 hours.
The
vessel completed the discharging operations at Vishakhapatnam on 21 May
at 03:45 hours and then sailed to Haldia to discharge the balance
quantity of cargo.
The shipowner calculated the laytime on the basis
of the NOR tendered on 12th May at 09:45 and claimed the payment of
demurrage charge for the time spent by the vessel in excess of the
laytime.
Steel Authority of India Ltd. rejected the demurrage claim
on the grounds that it accepted the vessel`s NOR only from the time when
all the four cranes along with the four grabs were made available in
operational condition on 20th May.
The second cargo was shipped on
board the vessel "Navios Kypros". The cargo quantity on board the vessel
was 53,731.008 MT of which a quantity of 25,743 MT had to be discharged
at Vishakhapatnam and the balance of 27,988.088 MT had to be discharged
at Haldia.
The vessel arrived at Vishakhapatnam and tendered NOR at
14:00 hours on 28th July 2008. The vessel berthed on 31 July 2008 at
11:30 hours and commenced discharging at 15:30 hours. On 1 August 2008,
the crane no.2 suffered a breakdown during discharging operations which
could not be repaired during the time spent at Vishakhapatnam. The
discharging operations at Vishakhapatnam were completed with the
available cranes on 2 August 2008 at 21:30 hours.
Thereafter, the
vessel sailed to the port of Haldia where it arrived and tendered NOR at
19:00 hours on 4 August 2008. The vessel berthed at 02:30 hours on 5
August 2008 and commenced discharging operations at 04:15 hours on the
same day.
The non-functional crane was repaired and made functional only at 12:50 hours on 8 August 2008.
The discharging operations at Haldia were completed at 10:00 hours on 9 August 2008.
The
shipowner calculated the laytime on the basis of the NOR tendered on
the vessel`s arrival at Haldia on 4 August 2008 and claimed the payment
of demurrage charge for the time spent by the vessel in excess of the
laytime.
Steel Authority of India Ltd. rejected the claim on the
grounds that it accepted the NOR tendered at Haldia only from the time
when all the four cranes along with the four grabs were made available
in operational condition, i.e. on 8 August 2008.
The dispute concerned the meaning of the following charter party clauses:
"35. Time counting provision:
At
each discharging port, even if at second discharge port vessel arrives
on demurrage, time to count 24 hours after Notice of Readiness is served
on arrival of the vessel within port limits at each port of discharge
and whether in berth or not and free pratique and ready in all respects to discharge the cargo. If turn time of 24 hours expires on Saturday afternoon, laytime will commence at 8.00 hours on first working day.
40. In
the event of breakdown of gears/cranes and other equipment of the
vessel by reason of disablement or insufficient power etc., the period
of such insufficiency shall not count as laytime.
43.
Charterers guarantee to discharge the cargo at the average rate of
10,000 metric tons Vizag/Paradip, 12,000 metric tons Haldia, basis 5
hatches (served by minimum 4 cranes all minimum 25 tons each with
minimum 10 CBM grabs) and pro rata if less, per weather working day of
24 consecutive hours, Sundays and holidays included (SHINC) provision to
be applicable after commencement of laytime.
44. Owners
guarantee that vessel has minimum 4 number of cranes each of capacity
minimum 25 tons and minimum 4 number of grabs each of minimum 10 cubic
meters capacity with cycle time of 4 minutes and serving all hatches and
accordingly the minimum capacity to discharge is 12,000 tons per day of
24 consecutive hours. Owners also guarantee that vessel has fully
automatic grabs [...]
A joint survey shall be conducted in order
to ascertain the particulars of cranes and grabs as above. In the case
of any deficiency, the surveyors` report shall be binding on the Owners
and Charterers and the rate of discharge shall be reduced
proportionately ..."
The charterers contended that the vessel
"Nord Fighter" had to be ready in all respects to discharge the cargo
at the time of tendering the NOR at Vishakhapatnam, with all the
discharging equipment ready. The subsequent repair of the non-functional
crane did not validate the NOR tendered at anchorage.
Similarly, the
vessel "Navios Kypros" had to be ready in all respects to discharge the
cargo at the time of tendering the NOR at Haldia on 4 August 2008, with
all the discharging equipment ready. The subsequent repair of the
non-functional crane on 8 August did not validate the NOR tendered on 4
August.
The arbitral tribunal held that the words "ready in all
respects to discharge the cargo" in Clause 35 of the contract of
affreightment did not state that all the cranes should be available for
discharge, nor did it state that the vessel should be ready to discharge
the cargo at the discharge rate provided in the contract of
affreightment. It was sufficient that the vessel to be capable of
discharging the cargo.
Thus, even if the vessels "Nord Fighter" and
"Navios Kypros" arrived with a non-functional crane, they were ready to
discharge the cargoes on board, though not at the rate stipulated in the
contract of affreightment.
Notwithstanding the breakdown of one
crane, the whole cargo quantity could be discharged using the other
functional cranes. The breakdown of one crane did not prevent the
discharge of cargo, but merely reduced the rate of discharge.
If the charterers could commence and complete the discharge of cargo with the available cranes, "it
would be absurd to say that the consequence of breakdown of a crane …
is that laytime does not count at all after tender of NOR", when the
only consequence of non-availability of crane is a proportional
reduction in discharge rate during the period of breakdown.
As long
as the vessel`s functional cranes can be used for discharging the cargo
from all the holds, the time counts. During the crane breakdown period
the time shall count on a pro rata basis in function of the number of
cranes available for the discharge operations.
Only if the vessel
arrives with all cranes defective, NOR is invalid, because in such case
the vessel would be totally unable to discharge the cargo.
Commentary
There
is a distinction between the clauses which require the vessel to be
ready in all respects to commence discharging the cargo as per the
discharge rate agreed in the charter party or CFR sale contract, with
all generators, cranes and grabs in good working condition and the
clauses which require the vessel to be ready in all respects to
discharge the cargo.
The first type of clauses include the
requirement that the vessel`s generators be able to provide continuous
and sufficient electric power to the vessel`s cranes and the requirement
that the vessel`s cranes be able to serve all cargo holds, work
simultaneously and continuously with lifts of the minimum capacity
stated in the contract (charter party or CFR sale contract). If after
berthing, the surveyors discover a deficiency to the generators that
will affect the continued normal discharge operations or to the cranes
and/or grabs that will affect their discharging capacity, then the
vessel will not be considered ready to discharge and the time lost until
the remedy of deficiency will not count as laytime or time on
demurrage. If nonetheless, the charterers or CFR buyers commence
discharging the cargo with the available cranes and grabs, this shall be
considered a waiver on the reliance on the condition of contract and
the time shall count pro rata in function of the number of cranes
available for the discharge of cargo.
In the second type of clauses,
the geared vessel`s readiness to discharge does not necessarily mean
that the vessel`s gears must be ready to discharge the cargo at the
contractual rate or that all the vessel`s cranes and grabs must be
available for commencing the discharging operations.
If the vessel`s
discharging equipment is not fully functional but the vessel is ready to
commence discharging operations from all the holds with the functional
cranes and grabs, the vessel is still considered ready to discharge the
cargo, even though not at the contractual rate.
The Computation Of Time Spent By The Geared Vessel Waiting For Berth
In case of the first type of vessel readiness clauses,
the vessel`s failure to provide the discharging equipment at the
required capacity after berthing will entitle the cargo receivers to
claim the deduction of time lost subsequent to berthing until the vessel
is in fact ready to commence discharging the cargo with all cranes and
grabs in good working condition. But the time lost by the vessel at
anchorage counts in full, because the Master and crew cannot arrange the
discharging equipment, including fitting the grabs into cranes, before
berthing.
In 2012 Indian law case Great Eastern Shipping Company v. Steel Authority of India Ltd.
the vessel "Jag Rishi" had to wait for berth from the time of arrival
in port on 5th February 2008 until 12th February 2008. After berthing,
two grabs needed repairs. One grab was fixed after 45 minutes, but the
second grab was ready after 11 hours and 45 minutes.
The shipowner
calculated the laytime on the basis of NOR tendered on 5th February and
claimed the payment of demurage charge for the time spent by the vessel
in excess of laytime.
The voyage charterer rejected the demurrage
claim. The charterer contended that since the full discharging equipment
was not available for use at the time of berthing on 12th February, it
means that the vessel was not ready in all respects to discharge the
cargo at the time of tendering the NOR on 5th February 2008 and
therefore, the laytime commenced only from the time when all the four
gears were fully operational, i.e. at 14:30 hours on 12th February.
The High Court of New Delhi held that:
"Merely
because some of the equipments were non-functional at the commencement
of discharge did not necessarily mean that they were non-functional even
at the time the NOR was served. […]
In a port charter when such NOR
is issued it is normally some days before the actual berthing. If some
of the equipments were temporarily non-functional at the commencement of
discharge, it did not mean they were in that position even when the NOR
was issued. […] It was not possible to anticipate [at the time of
tendering NOR] any partial failure of the cranes and grabs [after
berthing]."
The degree of readiness of geared vessels at the
time of arrival in port would depend on that of charterers or consignees
to do their part of the work.
Quoting a paragraph from "Scrutton on Charterparties" 17th Edition, the High Court of New Delhi held that:
"the
ship need not be absolutely ready by having all her gear fixed up for
the work at a time when the charterers or consignees are not in a
position to do any of their part of the work, so long as the ship can be
absolutely ready as soon as they are."
In case of the second
type of vessel readiness clauses, the vessel`s failure to provide the
full discharging equipment at the required capacity after berthing will
entitle the receivers to claim the deduction of time on a pro rata basis
in function of the ratio between the cranes/grabs in breakdown and the
total number of cranes/grabs. But the receivers are entitled to claim
the pro rata deduction not only from the time lost after berthing but
also for the time lost waiting for berth.
In 2014 case Steel Authority of India Ltd. v. Dampskibaselsbaket Norden A/S,
the High Court of New Delhi held that in a port charter party the time
lost by the vessel waiting for berth will count in the same way as the
time spent by the vessel at berth. The excepted periods, which are not
to be counted if the vessel would be at berth, would also not count if
the vessel would be waiting for berth.
Since the vessel in that case
arrived at the port of discharge with only three functional cranes
instead of four, the charterer was entitled to a pro rata deduction from
the time spent by the vessel waiting for berth. Had the vessel not been
prevented from reaching the designated berth due to congestion in port,
the vessel would have been at berth in which case only 75% of the
laytime would have counted on the basis of the three functional cranes.
Therefore, for the time lost by the vessel waiting for berth, the
charterer should have been entitled to a similar reduction on account of
breakdown of one crane, as if the vessel were in berth.
The Court based its decision on the House of Lords decision in Aldebaran Compania Maritima S.A. Panama v. Aussenhandel AG Zurich (The "Darrah")1.
In
that case the House of Lords held that in the computation of the time
spent by the vessel waiting for berth, the vessel must be treated as if
she had been at berth and all such periods that would be excepted from
the computation of laytime if the vessel had actually been at berth were
to be excluded in the computation of the time spent by the vessel
waiting for berth. The shipowner should not gain a greater advantage
from his ship being kept waiting for berth than it would get from the
ship being kept at berth.
by Vlad Cioarec, International Trade Consultant
This article has been published in Commoditylaw`s Coal Trade Review Edition No. 3.
Endnotes:
1. [1976] 3 Lloyd`s Rep. 320